Kaishan Information|SMGP successfully completed T-13 drilling and completed well testing

  On June 7, 2023, the SMGP Drilling and Resource Team conducted a completion test on the well T-13, which took 27 days and was completed on June 6. The test data shows that: T-13 is a high-temperature, high-fluidity production well, and successfully produced the heat source lost due to the failure of T-11 workover. The water absorption index of the well is between 54.76kg/s/bar and 94.12kg/s/bar, and the highest downhole temperature was recorded at 217.9°C 4.5 hours after the water injection was stopped. When the production layer is stable at 300°C, the well is expected to produce 190 tons/hour of high-pressure steam.

20230613083406_1562520230613083423_52055

  The total drilling cost of T-13 is less than US$3 million, and it is a low-cost high-production geothermal well. Its heat source will be used in the third phase of SMGP power station.

20230613083451_82180

  At present, the drilling rig is moving to the wellhead of T-07 well, and will start drilling the side channel of this well soon. Earlier, well T-07 was used for recharge because the casing could not be pushed down as planned and the shaft collapsed, which prevented the resources from being transported to the ground smoothly.


Post time: Jun-27-2023